If you followed my previous posts Deploying the vRealize suite using VCF 4.0 and vRealize Lifeycycle Manager (vRSLCM) enable product dowloads you should now have vRA and vIDM already downloaded.
In my previous post i went over the installation of vIDM which is a pre requisite for vRA. You can find the link here
Next, we need to create a new environment that will be used to deploy vRA. For this we can go to Lifecycle Operations -> Create Environment. Fill in the necessary information and click next
Select vRealize Automation, select the version and install type then click next
Review and accept the EULA then click Next
Next screen is the key. Click on Select and select the vRA key from the inventory. If we need to add the key manually we can follow the steps in my post here
Verify the key selection click on Validate Association and click on next
Select the certificate and click next. If a new certificate needs to be create follow the instructions on my post here
Make the proper selections for where the vRA server will get deployed and click Next
Fill in the proper network configuration and click next
Specify the proper network configuration for the product and click next
Run the precheck and verify that everything is green then click Next
Verify the summary and click submit
Next we are taken to the request details where we can follow the process that LCM is performing for us automatically.
We can see that the task completed
If we go to environments we can see that the vRA Environment